E.T.& L. Corp. has been subcontracted to perform sitework for a new gas company training facility in Shrewsbury. The contract, totaling $5 million, includes clearing and grubbing of the area, stripping topsoil, site cuts and fills of 180,000 cy, rip rap slope stabilization, furnishing and installing gravel for sidewalks and bituminous paving base, and furnishing and installing the site drainage system and concrete curb. Construction of the training center's foundation will begin in April 2017. Drainage is scheduled to be complete and the site will be at rough grade by the end of May 2017. The facility will be one of four new training centers which will feature hands-on labs, simulator areas, and an outdoor mock neighborhood, where gas company instructors can create a variety of emergency training scenarios.