Chesterfield - Ireland Street Bridge

E.T.& L. Corp. is currently working on a MassDOT project to replace the Ireland Street Bridge in Chesterfield, MA, which leads to the famous Chesterfield Gorge Reservation. The $2.8 million project was awarded to E.T.& L. in March, 2018. Work includes the construction of precast concrete box beams, deck panels, stub abutments on spread footings, riprap for scour protection, minor realignment and widening for roadway approaches, full-depth pavement, drainage improvements, and more. The project will be completed in 100 days, and is expected to be complete by November, 2019.